Production followup

Planning

Planning is made automatically by the scheduler according to the dates and priorities planned of all the confirmed kinds of production. It's also the scheduler which is in charge of supply proposing (internal picking list) for manufacture.

When the responsible for production connects himself, it can obtain the proposal for a scheduler planningvia the menu: G.P.A.O. > Work orders > Production Orders Waiting Goods. Then it can modify the different orders to change the planned manufacture date.

Workcenters followup

The production planning is done with infinite capacity. It doesn't take account into the possibly limited resources of each workcenter. That makes it possible to produce each day more or less that the maximum capacity. That also makes it possible to use planning without to define all the workcenters and all the tools taking place in a production.

To control the planning validity, the production responsible can select the workcenters which it wishes to analyze via the menu: G.P.A.O. > Definitions > Workcenters. Once the list selected, Put you in list mode and click on the 'print' icon to ask for a graph of the future load for the selected stations.

Tiny ERP asks for the analysis type (day per day, week per week or month by month) and if you wish to analyze the cycles or times. Once these data completed, the graph of the following figure is generated.

This graph allows to check that human resources won't have to work more 8h per day to remain in projected planning. You can calculate again this graph after each dates modification in the work orders.